Completed project

Foundation Pit, Soniachnyi Residential Complex

Soil excavation for the foundation of a 16-storey residential complex. Volume: 8,400 m3. The pit was completed in 12 working days and handed over to the developer with a full documentation package.

Location
Period Spring 2023
Type of work Residential construction
Equipment
Розробка котловану ЖК Сонячний — екскаватор та самоскид Completed site
Order

Need equipment for a similar project?

Describe your task — we will help select the equipment, operator and calculate the cost for your project.

Soil excavation for the foundation of a 16-storey residential complex. Volume: 8,400 m3.

The pit was completed in 12 working days and handed over to the developer with a full documentation package.